Pinecrest has three park projects underway this fall, and each one is at a different stage. Veterans Wayside Park on Pinecrest Parkway is done. Gary Matzner Park, on Kendall Drive at the Village's northern entrance, is close to opening, but its target date has moved every time the Village has updated it. Aleyda Mas Park, on SW 60th Avenue, is only now breaking ground and won't open until late 2027. If you're planning a weekend around any of them, only the finished one has a date you can count on.
Finished: Veterans Wayside Park
The Veterans Wayside Park beautification project was finished in August 2026. The park runs along Pinecrest Parkway between SW 110 Street and SW 112 Street.
According to the Village's September 2026 Pinecrest Sun, the project added:
- An enhanced Veterans Memorial and more gathering space for events and reflection
- ADA-compliant pathways
- A new playground for children ages 2 to 12
- A stone wall that works as both seating and a decorative barrier
- A bioswale system that filters stormwater into the existing pond
- Native landscaping that also helps manage runoff
The park's first major public event since the makeover is the Village's Veterans Day Ceremony at 9 a.m. on Wednesday, November 11. The program includes an Honor Guard, a pinning ceremony, music and a free breakfast.
The other finished piece this fall is a sculpture. Traversal, by artist Michael Szabo, was installed in September 2026 at Old Cutler Road and SW 120th Street, in a pocket park the Village calls one of Pinecrest's historic crossroads. It's made of 29 columns of bronze, corten steel and textured glass. The Village says light filters through the piece and the view changes as you walk past it.
Both of these are open now, and you don't need to check a construction schedule before you go.
Almost Open: Gary Matzner Park, Where the Dates Keep Moving
Gary Matzner Park sits on a 3.76-acre site at 6610 N. Kendall Drive, on the southeast corner between SW 67 Avenue and SW 65 Court. It's named for Gary C. Matzner, Pinecrest's second mayor, who the Village calls its founding father.
The Village Council approved buying the two parcels in 2021 and approved a concept design in May 2023. The final design adopted by the Council includes:
- Large open spaces and natural play areas
- A covered playground and a walking path
- A restroom shelter and parking
- Many preserved specimen trees, with all-native landscaping
- A gateway at the northern entrance to the Village
The location is the point. Drivers coming south on Kendall Drive hit this corner first, so the park will be the first thing they see of Pinecrest.
The opening date is less settled. Here is how the Village's own projections have changed:
| When the Village said it | What it projected |
|---|---|
| July 2024 | Ceremonial groundbreaking held July 12 |
| September 2024 Pinecrest Sun | Construction to start "by mid-winter" |
| Project page | Construction actually began August 2025 |
| March 2026 Pinecrest Sun | Opening in summer 2026 |
| September 2026 Pinecrest Sun | Opening in fall 2026 |
| Project page | Opening in October 2026 |
The ceremonial groundbreaking came more than a year before any construction started. Since then, the opening target has moved from summer to fall to October. As of late October, the Village's parks directory still listed Gary Matzner Park as a "Future Park Site," with no ribbon-cutting date and no posted hours. The park is clearly close. It just doesn't have a firm date yet.
The Kendall Drive Crosswalks Run on Their Own Schedule
The Village scheduled construction to begin Monday, October 26, on six raised crosswalks with decorative pavers along Kendall Drive (SW 88th Street). Each one goes where a neighborhood street meets the new shared-use path. The Village says the raised design makes walkers and cyclists easier for drivers to see.
According to the Village's October 13 traffic notice, each crosswalk takes about a month. The estimated order is:
- SW 64th Court, starting October 26
- SW 63rd Court, late November
- SW 62nd Court, late December
- SW 61st Court, late January
- SW 60th Avenue, sometime after January 1, date to be confirmed
- SW 65th Court, February
The Village expects the whole project to finish in February or March of 2027, and says dates may shift with weather and field conditions.
The last crosswalk on the list, at SW 65th Court, is the street on the park's eastern edge. So even if Gary Matzner Park opens on time, the crosswalk next to it probably won't be built until early 2027.
While a crosswalk is under construction, the work zone is closed to both people and cars. Residents can still reach their homes the whole time. On SW 60th Avenue through SW 64th Court, the alternate route is SW 92nd Street. On SW 65th Court, the Village will phase the work so the cul-de-sac stays open.
Just Starting: Aleyda Mas Park
Aleyda Mas Park is the slowest of the three. It's a 5-acre property at 11855 SW 60th Avenue, near SW 120 Street. The Montgomery family, who founded Fairchild Tropical Botanic Garden, owned it first. The Mas family owned it next, and the Village bought it in 2024. When the Village announced the purchase, it described the property's existing trails, lagoon, resort-style home, and mix of exotic and native trees.
The plan is a park for picnics, walks and time outdoors. The Village also says it will host "small-scale, high-end programs and activities for adults 18 and older."
Here's where the schedule stands:
- Construction contract: awarded to Waypoint Contracting on April 14, 2026, according to the project milestones on Your Voice Pinecrest
- Groundbreaking: "this fall," according to the September 2026 Pinecrest Sun
- Opening: fall 2027 in a July 2026 Village release, and November 2027 in the project milestones
The Village says this park will help meet the Council's goal of putting green space within one mile of every resident, or about a 10- to 15-minute walk from home. Gary Matzner Park took about a year from the start of construction to its October target, and that target was still slipping. With that in mind, treat November 2027 as the Village's best estimate, not a firm date.
The Dates You Can Put on Your Calendar
The dates that hold up this fall are for events at finished places and for crosswalk construction the Village has already scheduled:
- October 26 through late November: crosswalk work at SW 64th Court and Kendall Drive. Use SW 92nd Street to get around it.
- Wednesday, November 11, 9 a.m.: Veterans Day Ceremony at Veterans Wayside Park, with a free breakfast.
- Late November: crosswalk work moves to SW 63rd Court.
- Select nights, December 4 to 27, 6:30 to 10 p.m.: Nights of Lights at Pinecrest Gardens, with light displays, children's story time, crafts, vendors and some Santa and Grinch appearances. The Gardens says ticket sales are coming soon and details may change.
For Gary Matzner Park, keep an eye on the Village's parks directory. When "Future Park Site" disappears from the listing, the park is open.
If you live near Kendall Drive, Pinecrest Parkway or SW 60th Avenue and want to know how your home compares to others on your street as these projects wrap up, The Firm A Real Estate Brokerage can put it in local context for you, in English or Spanish. Request Your Free Home Valuation.